  1. Roll Call (jreznik, 17:01:09)
  2. Purpose of this meeting (jreznik, 17:06:29)
    1. Purpose of this meeting is to see whether or not F21 Final is ready for shipment, according to the release criteria. (jreznik, 17:06:29)
    2. This is determined in a few ways: (jreznik, 17:06:32)
    3. No remaining blocker bugs (jreznik, 17:06:33)
    4. Release candidate compose is available (jreznik, 17:06:34)
    5. Test matrices for Final are fully completed (jreznik, 17:06:36)
    6. http://qa.fedoraproject.org/blockerbugs/milestone/21/final/buglist (jreznik, 17:06:37)
    7. https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Installation (jreznik, 17:06:39)
    8. https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Base (jreznik, 17:06:40)
    9. https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Desktop (jreznik, 17:06:42)
    10. https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Server (jreznik, 17:06:43)

  3. Current status (jreznik, 17:07:27)
    1. Fedora 21 Final RC5 available for go/no-go decision (sgallagh, 17:08:46)
    2. 0 blocker bugs currently proposed (sgallagh, 17:08:57)
    3. All current blocker bugs are marked VERIFIED or CLOSED (sgallagh, 17:09:18)
    4. All currently accepted blocker bugs are marked VERIFIED or CLOSED (sgallagh, 17:09:38)
    5. https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Summary (roshi, 17:12:07)
    6. test matrices coverage looks pretty solid but it's not completed (jreznik, 17:12:22)
    7. Fedora QE is ok with test coverage (even not all test were covered due to limited availability of hw/setup) (jreznik_2nd, 17:56:11)

  4. Go/No-Go decision (jreznik_2nd, 17:56:53)
    1. AGREED: Fedora 21 Final status is go by Release Engineering, QA and Development (jreznik_2nd, 18:00:36)
    2. ACTION: jreznik to announce go decision and update releng ticket (jreznik_2nd, 18:01:50)

  5. open floor (jreznik_2nd, 18:01:55)
    1. readiness meeting will be held in one hour, the same channel (jreznik_2nd, 18:02:21)


Meeting ended at 18:11:44 UTC (full logs).

Action items

  1. jreznik to announce go decision and update releng ticket


Action items, by person

  1. jreznik
    1. jreznik to announce go decision and update releng ticket


People present (lines said)

  1. adamw (53)
  2. jreznik (48)
  3. roshi (37)
  4. sgallagh (30)
  5. jreznik_2nd (29)
  6. kparal (16)
  7. mattdm (15)
  8. danofsatx-work (13)
  9. zodbot (9)
  10. Southern_Gentlem (7)
  11. pwhalen (4)
  12. oddshocks (3)
  13. tflink (2)
  14. jsmith (2)
  15. sesivany (1)
  16. nirik (1)
  17. jalalsfs (1)
  18. gholms (1)
  19. jwb (1)


Generated by MeetBot 0.1.4.