#fedora-meeting-2: F21 Final Go/No-Go meeting
Meeting started by jreznik at 17:00:44 UTC
(full logs).
Meeting summary
- Roll Call (jreznik, 17:01:09)
- Purpose of this meeting (jreznik, 17:06:29)
- Purpose of this meeting is to see whether or
not F21 Final is ready for shipment, according to the release
criteria. (jreznik,
17:06:29)
- This is determined in a few ways: (jreznik,
17:06:32)
- No remaining blocker bugs (jreznik,
17:06:33)
- Release candidate compose is available
(jreznik,
17:06:34)
- Test matrices for Final are fully
completed (jreznik,
17:06:36)
- http://qa.fedoraproject.org/blockerbugs/milestone/21/final/buglist
(jreznik,
17:06:37)
- https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Installation
(jreznik,
17:06:39)
- https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Base
(jreznik,
17:06:40)
- https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Desktop
(jreznik,
17:06:42)
- https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Server
(jreznik,
17:06:43)
- Current status (jreznik, 17:07:27)
- Fedora 21 Final RC5 available for go/no-go
decision (sgallagh,
17:08:46)
- 0 blocker bugs currently proposed (sgallagh,
17:08:57)
- All current blocker bugs are marked VERIFIED or
CLOSED (sgallagh,
17:09:18)
- All currently accepted blocker bugs are marked
VERIFIED or CLOSED (sgallagh,
17:09:38)
- https://fedoraproject.org/wiki/Test_Results:Fedora_21_Final_RC5_Summary
(roshi,
17:12:07)
- test matrices coverage looks pretty solid but
it's not completed (jreznik,
17:12:22)
- Fedora QE is ok with test coverage (even not
all test were covered due to limited availability of
hw/setup) (jreznik_2nd,
17:56:11)
- Go/No-Go decision (jreznik_2nd, 17:56:53)
- AGREED: Fedora 21
Final status is go by Release Engineering, QA and Development
(jreznik_2nd,
18:00:36)
- ACTION: jreznik to
announce go decision and update releng ticket (jreznik_2nd,
18:01:50)
- open floor (jreznik_2nd, 18:01:55)
- readiness meeting will be held in one hour, the
same channel (jreznik_2nd,
18:02:21)
Meeting ended at 18:11:44 UTC
(full logs).
Action items
- jreznik to announce go decision and update releng ticket
Action items, by person
- jreznik
- jreznik to announce go decision and update releng ticket
People present (lines said)
- adamw (53)
- jreznik (48)
- roshi (37)
- sgallagh (30)
- jreznik_2nd (29)
- kparal (16)
- mattdm (15)
- danofsatx-work (13)
- zodbot (9)
- Southern_Gentlem (7)
- pwhalen (4)
- oddshocks (3)
- tflink (2)
- jsmith (2)
- sesivany (1)
- nirik (1)
- jalalsfs (1)
- gholms (1)
- jwb (1)
Generated by MeetBot 0.1.4.