#fedora-meeting: Fedora QA Meeting

Meeting started by adamw at 16:01:03 UTC (full logs).

Meeting summary

  1. Roll call (adamw, 16:01:10)
  2. Previous meeting follow-up (adamw, 16:05:12)
    1. "kparal to reply to the list with his suggestions for revisions to the proposed shutdown test case" - he did this, and we'll be coming back to the topic later (adamw, 16:06:18)
    2. "tablepc to do a new draft of the proposed test case after seeing kparal's suggestions" - this also happened, and once again we'll be coming back to it (adamw, 16:06:39)

  3. Proposed asynchronous blocker review process (adamw, 16:11:21)
    1. AGREED: there is a solid consensus that the async blocker process proposal is a good idea and we should go ahead and give it a shot (adamw, 16:19:26)
    2. ACTION: kparal to go ahead and set up some version of the proposed process for a trial run for early f32 review (adamw, 16:20:05)

  4. Proposed disk unmount test case (adamw, 16:22:17)
    1. https://fedoraproject.org/wiki/User:Tablepc/Draft_testcase_reboot (tablepc, 16:22:26)
    2. ACTION: adamw to send a reboot test case draft with some copyediting corrections to tablepc's draft (adamw, 16:31:21)

  5. F31 eclipse module default stream / protobuf issue (adamw, 16:39:02)
    1. late last week, the eclipse module was given a 'default stream' for F31; this means that module stream was now the default source for all packages it contains, rather than the non-modular repos (adamw, 16:42:45)
    2. it turned out the module included a build of the protobuf package, with some features removed; so now we had a reduced-functionality protobuf as the default. this caused problems for folks who had anything that required the missing bits of protobuf installed (adamw, 16:43:47)
    3. the default stream was quickly removed again, but the current implementation of modularity doesn't handle the removal of a default stream automatically - anyone who updated while it was set and got the module stream enabled is stuck with it until they deactivate the module manually (adamw, 16:45:09)
    4. the official recommendation from modularity team is to run `dnf module disable eclipse` followed by `dnf downgrade protobuf` (adamw, 16:46:50)

  6. Open floor (adamw, 16:56:15)


Meeting ended at 17:07:49 UTC (full logs).

Action items

  1. kparal to go ahead and set up some version of the proposed process for a trial run for early f32 review
  2. adamw to send a reboot test case draft with some copyediting corrections to tablepc's draft


Action items, by person

  1. adamw
    1. adamw to send a reboot test case draft with some copyediting corrections to tablepc's draft
  2. tablepc
    1. adamw to send a reboot test case draft with some copyediting corrections to tablepc's draft


People present (lines said)

  1. adamw (82)
  2. cmurf (24)
  3. lruzicka (23)
  4. tablepc (23)
  5. zodbot (10)
  6. coremodule (5)
  7. frantisekz (4)
  8. Southern_Gentlem (3)
  9. tflink (2)


Generated by MeetBot 0.1.4.